Strategic Objective 1:
Improve infrastructure and public services for a better living and recreation environment

1

SI 1.1

Urban and land use planning to preserve historic settlements

Municipality

1.1.1

Finalize the Urban and Land Use Plans for the Mulakhi town and Ushguli communities. The urban planning documentation for Ushguli has already been completed three years ago and has been submitted to UNESCO.

Mestia

Responsible Party

Estimated Budget

No cost

Estimate Timeline

Up to 3 years

Municipality

1.1.2

Prepare and obtain approval for Urban and Land Use planning that covers the entire administrative territory of Mestia and Lentekhi Municipalities.

Mestia, Lentekhi

Responsible Party

Municipal Council

Estimated Budget

No cost

Estimate Timeline

3 years

Municipality

1.1.3

Create a basic master plan and inventory for architectural and historical monuments as part of the Urban Planning Documents.

Mestia, Lentekhi

Responsible Party

Estimated Budget

No cost

Estimate Timeline

3 years

Results

Prevention of disorganized intrusion into the historical cultural fabric. Preservation of urban heritage. Compliance with architectural and urban requirements.

2

SI 1.2

Tourism infrastructure development in accordance with urban planning and development investment

Municipality

1.2.1

Coordinate the intentions of stakeholders and developers, while adhering to rules and regulations that reflect tourism development priorities.

Mestia, Lentekhi

Responsible Party

Estimated Budget

No cost

Estimate Timeline

Ongoing

Municipality

1.2.2

Mestia township center Seti: Complete the construction of the buildings and convert them into visitor service facilities, allocating space for the DMO visitors' center

Mesia

Responsible Party

Municipality and GoG

Estimated Budget

TBD

Estimate Timeline

3 years

Municipality

1.2.3

Feasibility study for the new year-round ski area: Mestia-Qoluldi Lakes-Chaladi glacier, covering a distance of up to 8.6 km.

Mestia

Responsible Party

Estimated Budget

500,000 EUR.

Estimate Timeline

1 year

Municipality

-

Construction of the ropeway (gondola) Mulakji-Tetnuldi, distance of 3 km

Mestia

Responsible Party

Estimated Budget

9 million EUR

Estimate Timeline

2 years

Municipality

-

Design and construct a recreation area/spa, and fun park near the airport

Mestia

Responsible Party

Municipality/ MDF

Estimated Budget

TBD

Estimate Timeline

3 years

Municipality

-

Feasibility study for Lentekhi - Mt. Chutkharo ski/mountain resort (development plan for a large 4-season resort)

Lentekhi

Responsible Party

Estimated Budget

TBD/In progress

Estimate Timeline

1 year

Municipality

1.2.4

Rehabilitate and adapt the existing historic-ethnographic museum for visitors interpretation center

Lentekhi

Responsible Party

Mayor/LSG/ Donor

Estimated Budget

100,000 EUR

Estimate Timeline

2 years

Municipality

1.2.5

Prepare a feasibility study for the Zeskho alpine camp, design the Ailama alpine camp, and undertake the reconstruction of the historical village of Makashi.

Lentekhi

Responsible Party

MDF/RDA-M oESD

Estimated Budget

RDA contracted E&Y/CDA

Estimate Timeline

Ongoing

Municipality

1.2.6

Plans for the development of new summer adventure tourism products and businesses such as ziplines, rafting and kayaking, camping, etc.

Lentekhi

Responsible Party

DMO/LSG

Estimated Budget

TBD

Estimate Timeline

5 years

Municipality

1.2.7

Conduct study for new oportunities for winter heliski and heli/ski-touring

Lentekhi

Responsible Party

DMO/LSG

Estimated Budget

TBD

Estimate Timeline

3 years

Results

New products for winter and summer activities. Tourism development priorities reflected in the annual plan/budgets of the respected national agencies/ministries/companies.

3

SI 1.3

Sustainable and quality energy supply

Municipality

1.3.1

Adopt an energy supply system tailored to the specific needs of tourism and residents, considering factors such as consumption patterns, residents and commercial users tariffs, and evaluating various technical and economic solutions.

Mestia, Lentekhi

Responsible Party

Estimated Budget

No cost

Estimate Timeline

5 years

Municipality

1.3.2

Conduct a feasibility study to increase the share of renewable energy, focusing on contributions and efficiency of small and medium-sized hydroelectric power plants (HHP)

Mestia, Lentekhi

Responsible Party

Private investment

Estimated Budget

TBD

Estimate Timeline

5 years

Municipality

1.3.3

Increase energy efficiancy for municipal buildings, domestic needs and private businesses

Mestia, Lentekhi

Responsible Party

Estimated Budget

TBD

Estimate Timeline

5 years

Municipality

1.3.4

Conduct a feasibility study, environmental and economic impact assessment for the construction of a natural gas supply infrastructure.

Mestia, Lentekhi

Responsible Party

GOG

Estimated Budget

TBD

Estimate Timeline

5 years

Results

Stable and reliable energy supply for the region, while also taking into consideration environmental and socio-economic needs.

4

SI 1.4

Roads and regional connectivity

Municipality

1.4.1

Rehabilitation of state road Zugdidi - Jvari - Mestia - Lasdili with ongoing maintanance works.

Mestia, Lentekhi

Responsible Party

Estimated Budget

TBD

Estimate Timeline

Ongoing

Municipality

1.4.2

Reconstruction of Ushguli - Zagaro pass-Tsana road.

Mestia

Responsible Party

Estimated Budget

TBD

Estimate Timeline

Ongoing

Municipality

1.4.3

Lentekhi interstate roads 102 km, 58 km paved form Lentekhi to Tsana,rehabilitation portion 44 km.

Lentekhi

Responsible Party

Estimated Budget

TBD

Estimate Timeline

Ongoing

Municipality

1.4.4

Lentekhi central road to villages paved total 28 km.

Lentekhi

Responsible Party

Estimated Budget

TBD

Estimate Timeline

Ongoing

Results

Secure the Kutaisi-Zugdidi circular road, passing through Upper and Lower Svaneti, to expand the tourist area and provide additional self-drive tourism opportunities.

5

SI 1.5

Public transportation

Municipality

1.5.1

Enhance public transport utilization and establish car-free zones in both the town and resort areas.

Mestia

Responsible Party

Estimated Budget

100,000 EUR

Estimate Timeline

3 years

Municipality

1.5.2

Arrange a circular and internal public transport of Mestia-Langer for both locals and tourists.

Mestia

Responsible Party

LSG & Private

Estimated Budget

100,000 EUR

Estimate Timeline

1 year

Municipality

1.5.3

Establish a bus station (public-private) in Mestia for tourist destinations.

Mestia

Responsible Party

Estimated Budget

50,000 EUR

Estimate Timeline

1 year

Results

Redistribution of tourist flows throughout the territory of Upper and Lower Svaneti. Improvement of residents’ mobility.

6

SI 1.6

National & international access

Municipality

1.6.1

Provision of Mestia Airport with modern navigation systems; Increase number of flights to minimum 2 per day.

Mestia

Responsible Party

Estimated Budget

TBD

Estimate Timeline

5 years

Municipality

1.6.2

Conduct feasibility study for the construction of a new airport in Chikhareshi/Lentekhi to assess technical and economic rationality.

Lentekhi

Responsible Party

Civil Aviation Agency/MoE SD

Estimated Budget

TBD

Estimate Timeline

3 year

Results

Increasing the frequency of regular flights and flight safety. Establishment of a new regional tourist hub.

7

SI 1.7

Water supply & wastewater

Municipality

1.7.1

Upgrade water supply and treatment system for Mestia municipality in 15 communities along the central road.

Mestia

Responsible Party

Estimated Budget

TBD

Estimate Timeline

TBD

Municipality

1.7.2

Rehabilitation of WS and WWS systems for big communities along the main road for community centers (Mestia 16, Lentekhi 6)

Mestia / Lentekhi

Responsible Party

LSG

Estimated Budget

2.5 million EUR

Estimate Timeline

5 years

Results

Significant improvement of communal services and minimization of environmental impact.

SI 1.8

Solid waste management

8

Municipality

1.8.1

Set up a small waste transfer station in Mestia municipality near the village of Lakhani.

Mestia

Responsible Party

Estimated Budget

500,000 EUR

Estimate Timeline

2 years

Municipality

1.8.2

Within the framework of "Kutaisi solid waste integrated management program" it set up a waste transfer station in Tsageri municipality, which will serve Lentekhi and Tsageri municipalities.

Lentekhi

Responsible Party

GOG

Estimated Budget

500,000 EUR

Estimate Timeline

2 years

Municipality

1.8.3

Municipalities to gradually introduce and operate waste collection systems for separate collection of municipal waste educational activity of the population for the transition to full-fledged waste separation.

Mestia / Lentekhi

Responsible Party

GOG/LSG/NG O

Estimated Budget

TBD

Estimate Timeline

4 - 5 years

Results

Increasing the efficiency of waste collection.